7.3

Topic 7

Development and testing

  • IGCSE I.C.T 0417
  • 2 min read
  • Syllabus 2026, 2027 and 2028

Objectives

  1. 1

    Testing

    • aThe need to test the system before implementation
    • bTest designs, test strategies, test plan (test data, expected outcomes, actual outcomes, remedial action) following testing
    • cTest designs including the testing of data structures, file structures, input formats, output formats and validation routines
    • dTest strategies including to test each module, each function and the whole system
    • eThe definition, characteristics and use of test data using normal, abnormal and extreme data
    • fThe use of live data

Cambridge IGCSE ICT 0417 syllabus 2026-2028, 7.3 Development and testing (copied for internal use as permitted by Cambridge)

Detailed · Deep study

1Why test?

The system is tested before it is used so that errors are found and corrected, and so that it is shown to meet the user requirements. Faults found after implementation are more costly and could cause data loss.

2Test designs and strategies

  • Test designs cover the data structures, file structures, input formats, output formats and validation routines.
  • Test strategies: test each module (part), each function (e.g. each button, each calculation), then the whole system working together.

3Test plans and test data

Part of a test plan for an age field (accepted range 11 to 18).
TestTest dataTypeExpected outcomeActual outcomeRemedial action
enter age15normalacceptedacceptednone
enter age25abnormalerror messageacceptedcorrect the range check
enter age11extremeacceptedacceptednone
enter ageabcabnormalerror messageerror messagenone
Type of test dataMeaning
normaldata that is within the acceptable range and should be accepted
abnormaldata that is outside the acceptable range or of the wrong type and should be rejected
extremedata at the limits of the acceptable range (the largest and smallest acceptable values) – should be accepted
live datareal data used by the organisation, used once the system has been tested with test data, to check it works in practice

4Exam focus

Key words: test plan; test data; normal; abnormal; extreme; live data; module; expected outcome; actual outcome; remedial action.

Quick self-check

Answer in your head first, then reveal.

  1. Normal e.g. 56 (1); abnormal e.g. 150 or −3 or "ten" (1); extreme 0 or 100 (1).

  2. Real data used by the organisation (1).

  3. Test data; expected outcome; actual outcome; remedial action (4).

Finished this subtopic? Track it on your subject page.